NOVO SALAVATSKAYA STEAM GENERATION PLANT

The project was implemented at Novo Salavatskaya CHP site. Steam generation unit PGU-410T makes it possible to produce thermal energy more economically and ensures the highest energy generation performance, with due consideration of the modernization of plants and putting new facilities in operation.

Ново-Салаватская ПГУ

2018 – 2019

Steam generation unit PGU-410T
(duty power: 410 MW – installed electric output capacity, 207 Gcal/h – installed output thermal capacity)

Revamping:

  • Rearrangement of gas conditioning unit of power generation plant PGU-410T
  • Retrofitting of diesel fuel feed process pipelines
  • Elimination of subsidence of gas metering unit and motor-road to block valve stations
  • Recultivation of infrastructure area
Completed activities:
  • Engineering survey
  • Proekt Design Documentation (PD)